The work on the bridge over Broad Street is about to make some major progress this weekend.
Contractors for the Tennessee Department of Transportation plan to connect the massive beams over the roadway, which means the road will be completely shut down starting at 8:00 o'clock this coming Friday (7/28/2017) evening and remain closed until 6:00 o'clock Monday (7/31/20917).
Murfreesboro City Manager Rob Lyons explains...
The roadway will be shut down a second time the following weekend, August 4th -7th, 2017.
The great news is that this $17.6 million T-DOT project is scheduled to be completed this coming December.