Ram's Road Forecast--Now through Feb. 8, 2020

  Email   Print

(MURFREESBORO) We're in the cold, dark and damp days of winter, and Murfreesboro Assistant Traffic Director Ram Balachandran checks his computer to create areas for 'Boro motorists to avoid between now and February 8, 2020.

City Construction Projects

Utility Crossing Work (John Lee Ln at Manson Pike)

Expected Road Closures: Monday through Friday, 6:00 am to 6:00 pm : Contractor for a private development will be performing utility crossing work on John Lee Ln at Manson Pike. Traffic on John Lee Ln will be detoured onto Cloverhill Dr, Brinkley Rd and Manson Pike. John Lee Ln will not be accessible from Manson Pike. Appropriate traffic controls and detours will be in place.

ADVERTISEMENT



City Traffic Signal Work

Veterans Pkwy at Franklin Rd

ADVERTISEMENT



Expected Lane Shifts: Monday through Friday, 9:00 am to 3:00 pm : City traffic signal contractor will be performing signal maintenance at the above intersections. There will be minor lane shifts and two-way traffic will always be maintained. Appropriate traffic controls will be in place.

Underground Fiber Optics Installation Work (Williams Dr and Kennedy Dr)

Expected Lane Closures: Monday through Friday, 9:00 am to 3:00 pm: Contractor for a private utility company will installing overhead fiber optic lines. There will be lane closures and traffic interruptions. Appropriate traffic controls will be in place.

Underground Fiber Optics Installation Work (E Lytle St and Spring St)

Expected Lane Closures: Monday through Friday, 9:00 am to 3:00 pm: Contractor for a private utility company will installing fiber optic lines along E Lytle St between N Church St and Spring St and On Spring St between E Lytle St and E Main St. There will be lane closures and traffic interruptions. Appropriate traffic controls will be in place.

Intersection Improvements at Old Fort Pkwy and Gresham Ln

Expected Lane Closures: Wednesday through Friday, 9:00 am to 3:00 pm: Contractor for a private development will installing right turn lanes and making roadway improvements. There will be partial lane closures and traffic shifts. Appropriate traffic controls will be in place.

Right Turn Lane Improvement Work (Old Fort Pkwy at Gresham Ln)

Expected Lane Closures: Saturday, February 1, 9:00 am to 3:00 pm: Contractor for a private development will be performing right turn lane improvements on Old Fort Pkwy at Gresham Ln. There will be lane closures and minor traffic interruptions. Appropriate traffic controls will be in place.

Annual City Street Paving Projects

Expected Lane Closures: Monday through Friday, 9:00 AM - 3:00 PM: City paving contractor will installing HC ramps at the following streets:

  1. Highland Ave at Bell St
  2. Highland Ave at Burton St

Expect lane shifts and traffic interruptions. Appropriate traffic controls will be in place.

TDOT Resurfacing Projects

RUTHERFORD COUNTY, The grading, drainage, construction of bridges, signals and paving on SR 99 from Cason Lane (L.M. 15.97 to I-24 in Murfreesboro (L.M. 18.12)

  • Daily, 9AM-4PM, There will be a lane closures WB to shift barrier rail at the Stones River bridge in order to prep barrier rail for concrete deck pour. One lane will remain open at all times.

RUTHERFORD COUNTY, I-24 SMART Corridor

  • Daily, 9AM-3PM, There will be a lane closure as needed between MM 79-80 for sign foundation work.

Source: TDOT

Read more from:
News
Tags: 
Murfreesboro, Ram Balachandran, traffic report, WGNS
Share: 
  Email   Print
Related Articles
Powered by Bondware
News Publishing Software

The browser you are using is outdated!

You may not be getting all you can out of your browsing experience
and may be open to security risks!

Consider upgrading to the latest version of your browser or choose on below: