Many construction projects in this area are nearing their deadlines, so crews are ramping-up the work. Traffic Engineer Ram Balachandran warns of potential traffic jams now through September 9th.

City Construction Projects

Bridge over Broad Street TDOT Project (Est Substantial Completion Dec, 2017)

ADVERTISEMENT



Expected Lane Closures: Tuesday through Friday, 8:00 pm to 6:00 am: There will be alternating lane closures on NW Broad Street, Memorial Blvd, Old Fort Pkwy and Ridgley Road for construction of the new Overpass. There will be lane shifts and traffic interruptions. At all times, one lane will remain open in each direction. Broadmor Blvd is closed to through traffic for construction work. W Lytle Street at Broad St is opened to traffic and is restricted to right-in and right-out movements only. Westbound traffic has been shifted to the north side to align with the newly constructed ramp. On Broad St, the northbound and southbound left turn movements can only be made during a protected turn signal phase. Appropriate traffic controls and detours will be in-place.

Middle Tennessee Widening Project (Greenland Dr to E Main St) (Est Substantial Completion August, 2018)

ADVERTISEMENT



Expected Lane Closures: Tuesday through Friday: Traffic on Middle Tennessee Blvd is reduced to two-lanes two-way between E Main St and Greenland Dr. E Lytle St is closed at Middle Tennessee Blvd. The section of E Lytle St between N Bilbro Ave and Middle Tennessee Blvd is only open to local traffic. Appropriate traffic control will be in place.

Rutherford County Judicial Center Project (between Burton St and Lytle St) (Est Substantial Completion June, 2018)

Expected Lane Closures: Wednesday, July 20, 2016 - June 30, 2018: As part of the Rutherford County Judicial Center construction, Burton St between Maple St and Church St will be closed to traffic to make roadway improvements. Burton St traffic will be detoured onto College St. Appropriate traffic controls will be in-place.

W Lytle Street Roadway Improvement Project (Baker St to Church St) (Est Substantial Completion Aug, 2018)

Expected Lane Closures: Tuesday through Friday: W Lytle Street will be closed to through traffic between Walnut St and Front St for construction work. N Maple St between W Lytle St and Olive St and W Lytle St between N Maple St and N Church St will be closed to through traffic until end of September 30, 2017. Access driveways to local businesses will be kept open. Appropriate traffic controls will be in place.

Maple St Alley Improvement Project (between W Main St and W Vine St) (Est Substantial Completion Sept, 2017)

Expected Lane Closures: Tuesday through Friday: The Maple St Alley will be closed to through traffic between W Main St and W Vine St for construction work. Deliveries to local businesses will be from Walnut St, W Vine St and Public Square. Appropriate traffic controls will be in place.

Sewer Installation Project (Manson Pike between Brookwood Ln and Rexland Pl) (Est Substantial Completion Sept, 2017)

Expected Road Closures: Tuesday through Friday, 9:00 am to 3:00 pm: Contractor for a private development will be installing sewer lines across Manson Pike. Traffic on Manson Pike will be reduced to one lane flagging operation. Appropriate traffic controls will be in place.

Medical Center Pkwy at GreshamPark Dr Turn Lane Improvement Project (Est Substantial Completion Sept, 2017)

Expected Lane Closures: Monday through Thursday, 7:00 pm to 6:00 am: The Contractor for the City of Murfreesboro will be extending the eastbound left turn lane on Medical Center Pkwy at GreshamPark Dr. Eastbound traffic on Medical Center Pkwy will be reduced from two lanes to one lane. All work will be done at night. Appropriate traffic controls will be in place. Westbound traffic will not be affected.

Medical Center Pkwy at Gateway Blvd Signalization and Turn Lane Improvement Project (Est Substantial Completion Dec, 2017)

Expected Lane Closures: Tuesday through Friday, 8:30 am to 3:30 pm: The Contractor for the City of Murfreesboro will be adding a westbound right turn lane on Medical Center Pkwy at Gateway Blvd. Westbound traffic on Medical Center Pkwy will be reduced from two lanes to one lane. Appropriate traffic controls will be in place. Eastbound traffic will not be affected.

Water, Irrigation and Sewer Installation Project (W Molloy Ln at S Molloy Ln) (Est Substantial Completion Sept, 21)

Expected Road Closures: Monday through Friday: Contractor for a private development will perform water, fire and sewer extension work on S Molloy Ln. Traffic on S Molloy Ln will be reduced to one lane flagging operation. Appropriate traffic controls will be in place.

Murfreesboro Water Resources Rehabilitation Work

  1. Grove Circle between Colgate St and RiverRock Blvd - 9/5 & 9/6
  2. RiverRock Blvd between Grove Circle and Maybrook Ct - 9/6 & 9/7
  3. 2306 Riverstone Dr between 2302 and 2310 Riverstone Dr - 9/7 & 9/8

Expected Lane Closures: Monday through Friday, 9:00 am to 3:00 pm: The contractor for Murfreesboro Water Resources Department will be making sewer manhole repairs. There will be lane closures and traffic interruptions. Appropriate traffic controls will be in place.

Annual City Street Paving Project

Expected Lane Closures: Monday through Friday, 9:00 AM - 3:00 PM: City casting contractor will be adjusting milling at the following street:

  1. Satinwood Dr between Thompson Ln and Tanglefoot Ct.
Read more from:
News
Tags: 
jams, Murfreesboro Traffic Engineer, Ram Balachandran, WGNS
Share: 
  Email   Print
Related Articles
Powered by Bondware
News Publishing Software

The browser you are using is outdated!

You may not be getting all you can out of your browsing experience
and may be open to security risks!

Consider upgrading to the latest version of your browser or choose on below: