Ram's Road Warrior "Character Builders" Through January 21st

Jan 14, 2012 at 06:17 am by bryan


Winter weather and road improvements continue. Murfreesboro Traffic Engineer Ram Balachandran warns of potential traffic character builders to be aware of through January 21st. 

City Construction Projects

ADVERTISEMENT

Maney Avenue Street Improvement Project (between SE Broad Street and College Street)

Expected Road Closures: Monday through Friday, 8 AM to 4:00 PM: Road construction work continues along Maney Avenue between E Castle St and E Main Street. The section of roadway between E Main and E Vine Street will be partially closed. Access drives to the local residents and businesses will be kept open at all times.Motorists are advised to use Highland Ave and Academy Street travelling north/south and State Street and Main Street travelling east/west. Work continues, minor traffic interruptions.

 Veterans Pkwy (New section between Barfield Road/Kimbro Road and Barfield Crescent Road)

Expected Lane Closures: Monday – Friday, 8:00 AM – 4:00 PM: The traffic on Barfield Crescent Road has been shifted to the south side near Lone Oak Drive. Appropriate lane shiftsigns and pavements markings are in-place. Contractor has started road work on the north side. The construction of the bridge over Stones River continues.Work continues, minor traffic interruptions. 

MTSU Phase 3 Project (Intersection of Greenland Drive at Wiles Ct)

Expected Lane Closures: Monday through Friday, 9 AM to 2:00 PM: There will be minor lane closures on Greenland Drive at Wiles Court. Traffic signal and roadway work continues intermittently at the intersection.There will be minor traffic interruptions.Work continues, minor traffic interruptions.

Atmos Project (Vine Street between University Ave and Maney Ave)

Expected Lane Closures: Monday - Friday, 9 AM to 3:00 PM: The contractor for Atmos will be installing gas lines along Vine Street between University Ave and Academy St. There will be partial lane closures and traffic interruptions on Vine Street.

Traffic Signal Work (Intersection of New Salem Highway and Veterans Pkwy)

Expected Lane Closures: Monday through Friday, 8 AM to 4:00 PM: Traffic signal installing work continues intermittently at this location. There will be minor traffic interruptions and partial lane closures. Appropriate traffic controls will be in-place. 

Traffic Signal Work (Intersection of Rutherford Blvd and Gold Valley Drive)

Expected Lane Closures: Monday through Friday, 8 AM to 4:00 PM: Traffic signal installing work continues intermittently at this location. There will be minor traffic interruptions and partial lane closures. Appropriate traffic controls will be in-place.

TDOT Intersection Improvement Project (Medical Center Pkwy between I-24 EB Off-Ramp and Asbury Lane)

Expected LaneClosures: Monday through Friday, 8:00 AM to 3:00 PM: The contractor for TDOT will be making on-ramp improvements and striping modifications on Medical Center Pkwy between I-24 EB Ramp and Asbury Lane. There will be alternate lane closures and traffic interruptions. One lane will remain open in each direction at all times.

Consolidated Utility District (CUD) Water Line Construction Project (County Farm Road between S Church Street and Annell Drive)

Expected LaneClosures: Monday through Friday, 8:00 AM to 5:00 PM: The contractor for CUD will be installing water lines pipes across County Farm Road between Annell Driveand Cedar Drive. This section of roadway will be closed between 8:00 am and 5:00 pm. Traffic on County Farm Road will be detoured onto Annell Drive, Hillview Road andCedar Drive. Driveway access to local residents between Annell Drive and Cedar Drive will be kept open at all times. Appropriate traffic controls will be in place.

Lytle Street Sewer Construction Project (Lytle Street between Church Street and Maple Street)

Expected Lane Closures: Monday - Friday: 7:00 AM to 4:00 PM: The contractor for the Water and Sewer Department will be laying sanitary sewer pipe on Lytle Street between Church Street and Maple Street. Lytle Street will be closed between Church Street and Maple Street. Traffic will be detoured onto Burton Street and College Street. Northbound and Southbound traffic on Church Street and Maple Street will not be affected. Driveway access to local businesses will be kept open at all times. Work continues, minor traffic interruptions.