Ram's 'Boro Traffic Through August 10, 2019

  Email   Print

(MURFREESBORO) Greener grass and more rain for the season, Traffic Director Ram Balachandran tells how this impacts motors traveling in the 'Boro now through August 10, 2019.

City Construction Projects

Middle Tennessee Widening Project (Greenland Dr to E. Main St)

ADVERTISEMENT



Expected Lane Closures: Monday through Friday: Traffic signal, landscaping, pavement marking, and incidental work continues between E Main St and Greenland Dr. Final paving and pavement marking work continues. Appropriate traffic controls are in place.

W Lytle Street Roadway Improvement Project (Baker St to Church St)

ADVERTISEMENT



Expected Lane Closures: Monday through Friday: W Lytle St is re-opened to traffic. Minor incidental construction work continues along W Lytle St, W College St and W Burton St. Appropriate traffic controls are in place.

Right Turn Lane Improvement Work (Thompson Ln at Old Fort Pkwy)

Expected Lane Closures: Monday through Friday, 8:30 am to 3:30 pm: City contractor will be making right turn lane improvements on Thompson Ln at Old Fort Pkwy. There will be lane closures and traffic interruptions. Appropriate traffic controls will be in place.

New Traffic Signal Installation Work (Fortress Blvd at Puckett Creek Crossing/Lone Wolf Run)

Expected Lane Closures: Monday through Friday, 9:00 am to 3:00 pm: City contractor will be installing a traffic signal at Fortress Blvd and Puckett Creek Crossing/Lone Wolf Run. There will be lane closures and traffic interruptions. Appropriate traffic controls will be in place.

Private Development Sewer Extension Work (Veterans Pkwy just north of SR 96/Franklin Rd)

Expected No Lane Closures: Monday through Friday, 9:00 am to 3:00 pm: Contractor for a private development will be installing sewer line across Veterans Pkwy. There will be minor traffic interruptions and no lane closures. Appropriate traffic controls will be in place.

Annual City Street Paving Projects

Expected Lane Closures: Monday through Friday, 9:00 AM - 3:00 PM: City paving contractor will raising castings, milling, pavement repairs, loop cutting and paving and striping on the following streets:

  1. College St between Maple St and Church St
  2. Church St between College St and Burton St
  3. Burton St between Maple St and Barker St

Expect lane shifts and traffic interruptions. Appropriate traffic controls will be in place.

TDOT Resurfacing Projects

RUTHERFORD COUNTY, SR 99 (New Salem Hwy) resurfacing from Cason Lane to I-24

  • Daily, 9AM-4PM, There will be alternating lane closures between the intersection of Barfield Drive and SR99 for the placement of bridge beams over West Fork Stones River. Appropriate traffic controls will be in-place.

RUTHERFORD COUNTY, The Resurfacing of SR 10 from Tiger Hill to North of Rutherford Blvd

  • Nightly, 8PM-5AM, There will be alternating lane closures on SR 10 (S Church St) between Tiger Hill and Rutherford Blvd in both directions for milling operation. One lane will remain open at all times.

Source: TDOT

Read more from:
News
Tags: 
2019, Aug. 10, Murfreesboro, Ram Balachandran, traffic, WGNS
Share: 
  Email   Print
Related Articles
Powered by Bondware
News Publishing Software

The browser you are using is outdated!

You may not be getting all you can out of your browsing experience
and may be open to security risks!

Consider upgrading to the latest version of your browser or choose on below: